I-215 Widening/Scott Rd to Nuevo Rd |
Description: In and near Perris, from Scott Road to Nuevo Road. Construct a third mixed-flow lane in each direction from Scott Road Interchange to Nuevo Road interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | Menifee, Perris |
Zip Code | 92571 |
Senate District |
28, 31 |
Assembly District | 61, 67 |
Congressional District | 41, 42 |
Caltrans District |
08 |
County/State Route | Riverside 215 |
Postmile Begin/End | R 14.2 28.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 10232 | 32,551 |
Lane Miles Added (HOV) | 21 | |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 675330 | 2,592,278 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Riverside County Trans Commission (RCTC) | Alex Menor | (951)787-7970 | amenor@RCTC.org | |
Design (PS&E) Phase |
Riverside County Trans Commission (RCTC) | Alex Menor | (951)787-7970 | amenor@RCTC.org | |
Right of Way Phase |
Riverside County Trans Commission (RCTC) | Alex Menor | (951)787-7970 | amenor@RCTC.org | |
Construction Phase |
Riverside County Trans Commission (RCTC) | Alex Menor | (951)787-7970 | amenor@RCTC.org | |
Corridor System Management Plan |
Riverside County Trans Commission (RCTC) | Alex Menor | (951)787-7970 | AMenor@RCTC.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $56,000 | $56,000 | ||||
CMIA |
$57,370 | $-18,591 | $38,779 | ||||
Non-bond Funding | |||||||
State/Federal* |
$65,392 | $-56,000 | $9,392 | ||||
Local** |
$22,240 | $-2,909 | $19,331 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $145,002 | $-21,500 | $123,502 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$9,392 | $0 | $9,392 | $6,045 | |||
Design(PS&E) |
$12,400 | $0 | $12,400 | $10,195 | |||
Right of Way |
$3,210 | $0 | $3,210 | $1,691 | |||
Construction |
$120,000 | $-21,500 | $98,500 | $92,038 | |||
Total* | $145,002 | $-21,500 | $123,502 | $109,969 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2008 04/13/2011 |
09/01/2007 04/12/2011 |
07/01/2008 04/13/2011 |
100 | 09/13/2007 04/13/2011 |
9 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/01/2011 05/07/2012 |
11/08/2010 06/20/2012 |
03/01/2011 05/07/2012 |
100 | 11/08/2010 05/22/2012 |
4 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
04/12/2011 05/07/2012 |
06/01/2011 05/07/2012 |
04/12/2011 05/07/2012 |
100 | 06/01/2011 04/23/2012 |
-2 0 |
|
Begin Construction Phase
End Construction Phase |
10/10/2012 12/13/2015 |
12/10/2012 12/28/2018 |
10/10/2012 12/31/2015 |
100 | 09/12/2012 10/03/2018 |
1 -34 |
|
Begin Closeout Phase
End Closeout Phase |
12/31/2015 06/30/2016 |
10/03/2018 10/03/2018 |
12/31/2015 06/30/2016 |
100 | 10/04/2018 06/30/2023 |
-34 -85 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 10232 | 32,551 |
Lane Miles Added (HOV) | 21 | |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 675330 | 2,592,278 |
Bond Funding Cost | |
---|---|
Adopted: |
$57,370,000 |
Current Approved: |
$38,779,000 |
Actual Expenditures: |
$37,484,000 |
Status as of December 31, 2023.