Caltrans Logo

I-215 Widening/Scott Rd to Nuevo Rd

Description: In and near Perris, from Scott Road to Nuevo Road. Construct a third mixed-flow lane in each direction from Scott Road Interchange to Nuevo Road interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Menifee, Perris
Zip Code 92571
 
Senate District
28, 31
Assembly District 61, 67
Congressional District 41, 42
 
Caltrans District
08
 
 
County/State Route Riverside 215
Postmile Begin/End R  14.2 28.5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  10232    32,551  
Lane Miles Added (HOV)      21  
Lane Miles Added (Mixed)      0  
Peak Period Time Savings (minutes)  675330    2,592,278  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Riverside County Trans Commission (RCTC) Alex Menor (951)787-7970   amenor@RCTC.org
Design (PS&E) Phase
Riverside County Trans Commission (RCTC) Alex Menor (951)787-7970   amenor@RCTC.org
Right of Way Phase
Riverside County Trans Commission (RCTC) Alex Menor (951)787-7970   amenor@RCTC.org
Construction Phase
Riverside County Trans Commission (RCTC) Alex Menor (951)787-7970   amenor@RCTC.org
 
Corridor System Management Plan
Riverside County Trans Commission (RCTC) Alex Menor (951)787-7970   AMenor@RCTC.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $56,000 $56,000
CMIA
$57,370 $-18,591 $38,779
Non-bond Funding
State/Federal*
$65,392 $-56,000 $9,392
Local**
$22,240 $-2,909 $19,331
Non Budgeted ETC
$0 $0 $0
 
Total**** $145,002 $-21,500 $123,502

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$9,392 $0 $9,392 $6,045
Design(PS&E)
$12,400 $0 $12,400 $10,195
Right of Way
$3,210 $0 $3,210 $1,691
Construction
$120,000 $-21,500 $98,500 $92,038
 
Total* $145,002 $-21,500 $123,502 $109,969

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2008 

04/13/2011 
09/01/2007 

04/12/2011 
07/01/2008 

04/13/2011 
100  09/13/2007 

04/13/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2011 

05/07/2012 
11/08/2010 

06/20/2012 
03/01/2011 

05/07/2012 
100  11/08/2010 

05/22/2012 


Begin Right of Way Phase

End Right of Way Phase
04/12/2011 

05/07/2012 
06/01/2011 

05/07/2012 
04/12/2011 

05/07/2012 
100  06/01/2011 

04/23/2012 
-2 

Begin Construction Phase

End Construction Phase
10/10/2012 

12/13/2015 
12/10/2012 

12/28/2018 
10/10/2012 

12/31/2015 
100  09/12/2012 

10/03/2018 


-34 
Begin Closeout Phase

End Closeout Phase
12/31/2015 

06/30/2016 
10/03/2018 

10/03/2018 
12/31/2015 

06/30/2016 
100  10/04/2018 

06/30/2023 
-34 

-85 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 10232 32,551
Lane Miles Added (HOV) 21
Lane Miles Added (Mixed) 0
Peak Period Time Savings (minutes) 675330 2,592,278

Bond Funding Cost
Adopted:
$57,370,000
Current Approved:
$38,779,000
Actual Expenditures:
$37,484,000

 

Status as of December 31, 2023.